A personal website that consolidates theme park operating calendars into a single full-month grid view. Starting with all Six Flags parks scraped from their website, expanding to any theme park via configurable scraper adapters, and eventually becoming a trip planning engine that suggests nearby parks and estimates travel costs.
Core Value
One place to see every park's open days — so planning a trip takes seconds, not a dozen browser tabs.
Requirements
Validated
(None yet — ship to validate)
Active
- Full month grid calendar showing open/closed days across all Six Flags parks
- Web scraper pulls park hours from sixflags.com (URL pattern:
/{park}/park-hours?date=YYYY-MM-DD) - Scraper adapter architecture so other park chains can be added with minimal new code
- Any theme park can be added via manual configuration (URL pattern + scraper adapter)
- Trip planner suggests nearby open parks given a target park and date range
- Drive time shown between parks
- Rough flight cost estimate via Google Flights for farther destinations
Out of Scope
- Booking / ticketing — just planning and discovery, not purchasing
- User accounts — personal use, no auth needed
- Real-time wait times or crowd levels — calendar/hours only
- Mobile app — web-first
Context
- Six Flags park hours follow a consistent URL pattern:
https://www.sixflags.com/{park-slug}/park-hours?date=YYYY-MM-DD - Other major theme park chains (Cedar Fair, Universal, Disney, Busch Gardens) have similar site structures — a reusable scraper base should cover most cases
- Trip planning example: planning King's Dominion → surface Busch Gardens Williamsburg as a nearby park that's also open
- Google Flights rough estimates (not bookable) are sufficient for V2 flight cost
Constraints
- Data: Web scraping — no official API, fragile to site redesigns; mitigate with adapter isolation so fixes are localized
- Audience: Personal use only — no need for scalability, auth, or uptime SLAs
- Tech: Website (browser-based); stack TBD during planning
Key Decisions
| Decision | Rationale | Outcome |
|---|---|---|
| Scrape over API | No public Six Flags API exists | — Pending |
| Adapter pattern for scrapers | Different parks have different HTML; reuse parsing logic where possible | — Pending |
| Personal use (no auth) | Just for the owner; no user management complexity | — Pending |
Evolution
This document evolves at phase transitions and milestone boundaries.
After each phase transition (via /gsd:transition):
- Requirements invalidated? → Move to Out of Scope with reason
- Requirements validated? → Move to Validated with phase reference
- New requirements emerged? → Add to Active
- Decisions to log? → Add to Key Decisions
- "What This Is" still accurate? → Update if drifted
After each milestone (via /gsd:complete-milestone):
- Full review of all sections
- Core Value check — still the right priority?
- Audit Out of Scope — reasons still valid?
- Update Context with current state
Last updated: 2026-04-03 after initialization